Why Permits Are Required
A solar installation involves both electrical and structural work on your property. Like any significant electrical or structural modification, it requires sign-off from the relevant authorities to confirm the work is done safely and in compliance with applicable codes.
In Quebec, three separate approvals are required before a system can be switched on: a municipal building permit, RBQ-licensed contractor credentials under the Quebec Construction Code, and a Hydro-Québec interconnection approval for grid connection.
The Municipal Permit and RBQ Licensing
Most Quebec municipalities require a building permit for rooftop solar on a residential property. This permit confirms the installation respects local zoning bylaws, the structural load capacity of your roof, and applicable construction codes.
Alongside that, the work must be done by contractors holding the right RBQ (Régie du bâtiment du Québec) licence subclasses. The electrical work is reserved for electrical contractors holding subclass 16, which are qualified by the Corporation des maîtres électriciens du Québec (CMEQ). Nuvia Energy holds subclasses 1.2 and 1.3 (general contractor), so it can take the whole project, and all electrical work on our installations is done by our subcontractor master electrician holding RBQ subclass 16 and member of CMEQ. Our guide to RBQ licences for solar explains who can do what.
Check Your Municipality's Requirements
Permit requirements vary by municipality, and some also require a PIIA (Plan d'implantation et d'intégration architecturale) review, a discretionary design review on top of the standard permit. We're building a database of these municipal requirements as we work with clients across Quebec, search for yours below.
Hydro-Québec Interconnection Approval
For your system to connect to the grid and for you to receive net metering credits, Hydro-Québec must approve your interconnection application. This process includes verifying meter compatibility, confirming the system meets their technical standards, and registering your installation for two-way billing.
This approval is typically what sets the overall project timeline: Hydro-Québec currently takes between 4 and 12 weeks to process a standard residential application depending on the season and workload. That's why we submit the interconnection application as early in the process as possible.
What Nuvia Handles for You
The administrative work is included in our turnkey service: the municipal permit, the Hydro-Québec connection request and the RBQ compliance documentation. For the LogisVert grant, applied for after installation, we prepare the documents the program requires and guide you through the application. You don't deal with multiple agencies: our team manages the process from start to finish.
We also keep you informed as each approval comes through, since waiting on government processing times is one of the less-predictable parts of the timeline. Transparency about realistic timelines is part of how we work.